April 20, 2020 Kym Graves

BLOG – Halfway There!

Selmon Extension construction crews have reached the halfway point setting segments for the construction of the new elevated bridge. Crews moved the launching gantry over the weekend at pier 18 with over 350 segments post-tensioned starting from the west end. Crews will end the segmental portion of the bridge at pier 36, with a total of 744 segments in place. With the segment erection work ongoing, the offsite casting yard has only 100 segments left to cast. Operations should wrap up early this summer.